Site inspection of the Projects under the Ghana Secondary Cities Support Programme (UDG2) at Obuasi Municipality

Last Updated on January 30, 2022 by Admin

Site inspection on of UDG 2 projects under the Ghana Secondary Cities Support Project (GSCSP) on storm drain from Born Again Junction to Nyameso and storm drain at Mensahkrom were held on Friday, 28TH January 2022 at the Obuasi Municipal Assembly for the members concerned to deliberate on issues related to the projects under UDG 2. The members present embarked on-site visit to inspect projects at LOT 1, 2 and 3. The Consultant explained the extent of the work done and further deliberated on other related issues. Officers appreciated the extent of the progress of work and findings and observation were also discussed. The consultant also made recommendations on the various LOTs during the visit.

The MCE also recommended the Contractors namely;

M/S Top Leader – LOT 1

M/S Malsons Construction Limited – LOT 2

M/S OBJ Construction Limited – LOT 3 for the good work done and urged them to adhered to the recommendation made by the Consultant to ensure quality work done.

 

Credit:  Mun. Planning Unit / OMA